Setting a new standard for sustainable logistics

Setting a new standard for sustainable logistics

SEKO Elektro delivered the complete electrical installation for Bulk Wood—a modern warehouse and logistics building where sustainable material choices, energy efficiency and precise project execution take centre stage.

Bulk Wood at Frogner was developed as a model for the next generation of warehouse and logistics buildings. With a glulam load-bearing structure, a sedum roof and a fossil-free construction site, the project demonstrates how modern commercial buildings can reduce their carbon footprint without compromising quality or operations. SEKO Elektro delivered the complete electrical installation.

About the project

Bulk Wood is a further development of Bulk’s standardised warehouse concept, replacing the conventional steel load-bearing structure with glulam to reduce the building’s carbon footprint.
The ambition was to create a modern logistics building with high energy efficiency, a fossil-free construction site and a recycling rate of at least 90% for construction waste. The result was a project that reduced the carbon footprint by 60%.

The delivery

  • Complete electrical installation
  • Lighting
  • Telecommunications and data
  • Fire alarm system
  • Emergency lighting
  • Technical advice

The results

  • 60% lower carbon footprint
  • Glulam load-bearing structure
  • Fossil-free construction site
  • Sedum roof
  • At least 90% sorting of construction waste
  • Energy-efficient warehouse building

Sustainable buildings start with good collaboration

Bulk Wood was developed with the aim of reducing its carbon footprint throughout the construction process. Replacing conventional steel structures with glulam significantly reduced emissions, while the building was also designed for energy-efficient operation and low operating costs.

SEKO Elektro delivered the complete electrical installation, including lighting, power outlets, telecommunications and data, fire detection and emergency lighting. The project was completed in close collaboration with property developer Bulk Industrial Real Estate and main contractor Thermica—a partnership that was essential to efficient execution and high quality throughout the project.

Digital planning enabled precise execution

The use of glulam placed particularly high demands on planning and coordination. The entire building was therefore modelled in 3D before construction began, allowing technical clashes to be identified and resolved early in the process.

The detailed modelling made it possible to address potential conflicts before work started. The result was precise execution and a building delivered without defects or outstanding issues.

Sustainable material choices

Glulam significantly reduced the building’s carbon footprint compared with conventional steel structures.

Precise planning

3D modelling made it possible to identify technical challenges before construction began.

Efficient execution

Close collaboration between the property developer, contractors and technical disciplines ensured high quality throughout the project.

A partnership built on trust

“We have worked with Bulk for several years and were delighted to be entrusted as the electrical partner for this project. We delivered the complete electrical installation, including lighting, power outlets, telecommunications and data, fire detection and emergency lighting. It has been an exciting project, with close and productive collaboration with both Bulk and Thermica throughout the construction period.”

Håvard Pedersen. Project Manager, SEKO Elektro

A building that sets a new standard

Bulk Wood was developed with ambitious environmental targets from the earliest planning meetings. Together with tenant Hilverda De Boer Norge, the project placed strong emphasis on energy-efficient operation, sustainable material choices and low lifecycle costs.

The original objective was to reduce the building’s carbon footprint by 40%. The final reduction reached 60%, demonstrating how focused planning and effective collaboration can achieve results beyond initial expectations.

Sustainable buildings are created together

Bulk Wood demonstrates how sustainable material choices, early collaboration and strong electrical expertise can reduce a building’s carbon footprint without compromising quality or operations. The project is a strong example of how long-term cooperation between the property developer, contractors and technical disciplines can create buildings that set a new standard for future warehouse and logistics developments.

Christoffer M. Ring-Larsen, Prosjektleder hos Bulk Industrial Real Estate AS

High expectations—delivered with quality

“We have completed several projects with SEKO Elektro, and our expectations are always high. They maintain an open dialogue and provide valuable advice to both us and the tenants. Their delivery exceeded our expectations in terms of service and efficient follow-up. When SEKO Elektro is involved, we receive not only what we ask for, but something more. It gives us confidence to work with SEKO Elektro, knowing that they have control of the entire project and understand the tenants’ needs.”

Christoffer M. Ring-Larsen
Project Manager, Bulk Industrial Real Estate AS