Technology when it matters most

Technology when it matters most

At the new emergency department at Telemark Hospital, Eltera Skagerrak has delivered technical solutions designed to support safe and reliable patient care – around the clock.

Technology for a critical public service

In an emergency department, the technical systems must work when they are needed most. Power supply, lighting, emergency lighting and fire detection must support healthcare professionals in their work while creating a safe environment for patients and their families.
Eltera Skagerrak played a key role in the development of the new emergency department at Telemark Hospital in Skien. The project placed high demands on operational reliability, technical coordination and an understanding of how the facility would be used.
Glamox supplied the lighting solutions and participated actively in the design process alongside Eltera Skagerrak, the hospital and the other project partners.

About the project

As the technical subcontractor, Eltera Skagerrak was responsible for the power and low-voltage electrical systems in the new emergency department at Telemark Hospital. The delivery includes a range of technical systems designed to ensure safe and reliable operation in a facility that must remain ready around the clock.
Eltera Skagerrak was also responsible for designing its own technical delivery. The project required extensive coordination and close collaboration across disciplines, with up to 13 electricians from Eltera Skagerrak working on site at the same time.

Services delivered

  • Power and low-voltage electrical installations
  • General and emergency lighting
  • Fire alarm and patient alert systems
  • Medical technology network
  • Emergency, standby and UPS power
  • System design and technical coordination
  • Testing, documentation and commissioning

Results

  • Reliable systems supporting continuous operation
  • Backup power for critical functions
  • Lighting adapted to employees and patients
  • Effective coordination between technical disciplines
  • Solutions designed to meet strict functional requirements
  • Technical systems developed for a critical public service

Operational reliability when it matters most

The technical systems in an emergency department must operate around the clock. The new department therefore incorporates redundant solutions and several levels of backup power, ensuring that critical functions remain available if the normal electricity supply fails.
A large number of technical installations also had to be coordinated within an area of only 1,170 square metres. Electrical, ventilation, plumbing and other technical systems had to share containment routes and the limited space above suspended ceilings. This required careful planning, technical coordination and continuous collaboration between the different disciplines.

When it matters most

“We deliver the technical solutions, but their function takes on a very different significance here than in many other buildings. We need to know that the people treating a patient have the power, lighting and systems they require.”

Stig Kvam
Project Manager, Eltera Skagerrak

Lighting designed for people and tasks

Lighting in an emergency department must meet a wide range of needs. Healthcare professionals require effective task lighting for demanding medical procedures, while patients and their families need surroundings that feel as calm and comfortable as possible.
In the corridors, the luminaires have been positioned along the walls rather than directly above patients. This prevents patients from having light shining directly into their eyes while being transported on a stretcher. Lighting in treatment rooms is adapted to the work being performed, while waiting areas have a calmer lighting environment.

Lighting designed for people

“We have considered both the people who will work here and those who arrive in a vulnerable situation.”

Hans Tore Reinholt
Sales Engineer, Glamox

Intelligent lighting control

Glamox supplied LED luminaires with lighting and daylight-responsive controls. Light levels can be adapted to the room, the available daylight and the task being performed. This provides the right lighting when it is needed while helping to limit unnecessary energy consumption.

Early collaboration creates better solutions

Glamox became involved during the design phase. Working with Eltera Skagerrak and the customer, the team clarified functional requirements and selected suitable solutions at an early stage. Short decision-making processes and close collaboration made it easier to resolve technical questions throughout the project.
For Eltera Skagerrak, quality also lies in the elements that are no longer visible once the facility enters operation – from containment routes and connections to coordination, documentation and execution.

Developing the solutions together

“Glamox participated in the design phase, attended customer meetings and helped us select the right solutions. Having a supplier behind us that provides support when we need it gives us confidence.”

Stig Kvam
Project Manager, Eltera Skagerrak